2021 C L C 488
[Islamabad]
Before Miangul Hassan Aurangzeb, J
PAKISTAN REAL ESTATE INVESTMENT AND MANAGEMENT COMPANY (PVT.)
LIMITED----Petitioner
Versus
Messrs SKY BLUE BUILDERS and another----Respondents
Civil Revision No.225 of 2019, decided on 10th December, 2020.
(a) Contract Act (IX of 1872)---
----Ss.126 & 128---Civil Procedure Code (V of 1908), O.XXXIX, Rr.1
& 2 ---- Commercial contracts --- Contract of performance guarantee, in the
form of a Bank guarantee ---- Grant of injunction / restraining order under
O.XXXIX, Rr.1 & 2, C.P.C., against encashment of an unconditional Bank
guarantee----Independence and autonomy of the contract of
guarantee---Scope---Petitioner impugned order of Trial Court whereby
respondent's application under O.XXXIX, Rr.1 & 2, C.P.C., seeking to
restrain petitioner from encashing Bank guarantee was allowed, until such time
Arbitration Tribunal determined whether or not respondent committed default of
contract----Contention of petitioner, inter alia, was that such guarantee was
made in a commercial contract, and was to be encashed as soon as petitioner
made declaration that respondent committed default of contract---Validity---For
purposes of making a demand for encashment of guarantee, it was explicitly
provided that petitioner shall be "sole and final judge" for deciding
whether the respondent had fully performed obligations under the contract or
defaulted on same---- Court could not rewrite contract of guarantee by making
encashment of same contingent upon finding of Arbitration Tribunal and none of
the terms of contract of guarantee were absurd, inconsistent or vague --- Trial
Court therefore made an error by issuing temporary injunction against
encashment of guarantee --- Impugned order was set aside --- Revision was
allowed, accordingly.
Shipyard
K. Damen International v. Karachi Shipyard and Engineering Works Ltd. PLD 2003
SC 191; Braganza v. BP Shipping Limited 2015 SCMR 742; System Company v. MTU
Middle East FZE PLD 2019 Sindh 382; Green Group of Hotels v. Municipal
Corporation, Peshawar 2017 MLD 257; Pakistan Industrial Credit and Investment
Corporation Ltd. v. Khairpur Sugar Mills Ltd. 2012 CLD 1192; Montage Design
Build v. The Republic of Tajikistan PLD 2015 Isl. 13; Standard Construction
Company (Pvt.) Limited v. Pakistan through Secretary Ministry of Communications
2010 SCMR 524; Husein Industries Ltd. v. Sui Southern Gas Company Ltd. PLD 2020
Sindh 551; Atlas Cable (Pvt.) Limited v. Islamabad Electric Supply Company Limited
2016 CLC 1677; Global Energy and Commodity Exchange Group Italy SPA (GECX
GROUP) v. Trading Corporation of Pakistan 2013 CLD 681; Mahatma Gandhi Sahakara
Sakkare Karkhane v. National Heavy Engg. Coop. Ltd. AIR 2007 SC 2176; Hindustan
Steelworks Construction Ltd. v. Tarapore & Co. AIR 1996 SC 2268 and
Hindustan Steel Workers Construction Ltd. v. G.S. Atwal & Co. (Engineers)
(Pvt.) Ltd. AIR 1996 SC 131 rel.
(b) Specific Relief Act (I of 1877)---
----Ss.56(f), 21 & 53---Civil Procedure Code (V of 1908), O.XXXIX,
Rr.1 & 2----Preventive injunctions---Temporary and preputial injunctions,
grant of---Contracts not specifically enforceable---Injunction could not be
granted to prevent the breach of a contract the performance of which would not
be specifically enforced---Scope---Contract which could not be enforced by a
decree for specific performance, could not be negatively enforced by issuance
of a temporary injunction.
Lahore
Stock Exchange Ltd. v. Hassan Associates 2010 MLD 800; District Council, Gujrat
v. Iftikhar Ahmad 1998 MLD 1461; Qasimabad Enterprises v. Province of Sindh
1998 CLC 441; Universal Trading Corporation (Pvt.) Ltd. v. Beechem Group PLC
1994 CLC 726 and PIA Corporation v. Hazir (Pvt.) Ltd. PLD 1993 Kar. 190 rel.
(c) Civil Procedure Code (V of 1908)---
----O.XXXIX Rr.1 & 2----Temporary injunction / interim relief, grant
of---Essential ingredients --- Adjudication of applications for temporary
injunction under O.XXXIX Rr.1 & 2, C.P.C.----"Irreparable loss"
meaning and scope of---Monetary loss could not be termed to be
"irreparable loss".
Dewan
Petroleum (Pvt.) Ltd. v. Oil and Gas Investment Limited 2019 CLC 1486 rel.
Barrister
Ummar Zaiuddin for Petitioner.
Barrister
Bilal Akbar Tarar for Respondent No.1.
Sadaqat
Ali Jehangir for Respondent No.2.
Dates
of hearing: 9th, 16th and 30th September, 2020.
JUDGMENT
MIANGUL
HASSAN AURANGZEB, J.----Through
the instant civil revision petition, the petitioner, Pakistan Real Estate
Investment and Management Company (Pvt.) Limited, impugns the order dated
17.05.2019 to the extent whereby the learned Civil Court allowed respondent
No.1's application for interim injunction under Order XXXIX, Rules 1 and 2 read
with Section 151, C.P.C., and directed the contesting parties to "maintain
status quo at the project site till the conclusion of the arbitration
proceedings." Furthermore, the petitioner was restrained from encashing
the performance guarantee furnished by respondent No.1.
2. The
facts essential for the disposal of this revision petition are that the tender
bidding process initiated through advertisement dated 23.08.2011 culminated in
the execution of the contract dated 24.01.2012 for the construction of a
commercial complex/apartments on Plot No.63A, M.A. Johar Town, Block 25, Trade
Centre, Phase-II, Lahore between the petitioner and respondent No.1's
predecessor-in-interest, M/s. Bhalli Constructors. For ease of reference,
respondent No.1's ansits predecessor-in-interest shall also be referred to as
"respondent No.1." Letter to commence works was issued to respondent
No.1 on 16.02.2012. The contract period was 20 calendar months (i.e. 04 months
for the design, and 16 months for the construction). In this way, the contract
completion date came to be 15.10.2013.
3. On
23.05.2012, the Lahore Development Authority ("L.D.A.") cancelled the
allotment of Plot No.63A on the ground that it was falling in the Right of Way
of the road proposed to be constructed from the Expo Centre to Khayaban-e-Jinnah.
The cancellation of the allotment caused respondent No.1 to suspend the works
on 24.05.2012. In lieu of Plot No.63A, the L.D.A., vide letter dated
09.06.2012, allotted Plot No.66 to the Employees' Old-age Benefit Institution
of which the petitioner is a wholly owned subsidiary. The allotment of Plot
No.66, which has a different acreage to Plot No.63A, did not result in the
cancellation of the contract dated 24.01.2012 or the initiation of a process
for re-procurement. The building designs for the project on Plot No.66 were
approved by the petitioner vide letter dated 26.06.2012, and the letter to
commence the works was issued to respondent No.1.
4. Clause
33 of the contract dated 24.01.2012 provided for any disputes between the
parties to the said contract to be resolved by making efforts to settle such
disputes. The said clause also provided that respondent No.1 should make a
request in writing to the Engineer-in-Charge for the settlement of disputes
within 28 days of arising of the cause of dispute, failing which no dispute
raised by respondent No.1 shall be entertained by the petitioner. Furthermore,
it was provided that if the disputes between the said parties still persist,
the settlement of the disputes may be sought through arbitration proceedings in
accordance with the provisions of the Arbitration Act, 1940 ("the 1940
Act").
5. Clause
32.1 of the contract dated 24.01.2012 required the successful bidder to furnish
a performance security within a period of fourteen days of the issuance of the
letter of acceptance. The performance security had to be furnished in the form
and the amount stipulated in the Bidding Data and the Conditions of Contract.
Pursuant to the said provision, performance guarantee for an amount of
Rs.51,864,749/- was furnished on 10.01.2012 by respondent No.2 (Jubilee General
Insurance Company Ltd.) on the instructions of respondent No.1.
6. Vide
letter dated 29.12.2017, respondent No.2 informed respondent No.1 that the
petitioner had made a demand for the encashment of the performance guarantee
for the entire amount of Rs.51,864,749/-. The petitioner's call for the
encashment of the performance guarantee prompted respondent No.1 to file an
application under Section 20 of the 1940 Act on 08.01.2018 before the learned
Civil Court against the petitioner and respondent No.2, praying for the
disputes and differences between the parties to the contract dated 24.01.2012
to be referred to arbitration. Along with the said application, respondent No.1
also filed an application for interim injunction seeking a restraint against
the petitioner and respondent No.2 from encashing the performance guarantee.
Furthermore, in the said application, respondent No.1 also sought an injunction
to restrain the petitioner from taking adverse action against respondent No.1.
7. Vide
ad-interim order dated 08.01.2018, the learned Civil Court restrained the
petitioner from encashing the performance guarantee and from taking any adverse
action against respondent No.1.
8. The
disputes and differences between the petitioner and respondent No.1 with
respect to the progress of work caused the petitioner to call upon respondent
No.1, vide letter dated 17.07.2018, to vacate the project site. Apparently,
respondent No.1 had applied for an extension in time which had not been acceded
to by the petitioner. Subsequently, vide letter dated 13.08.2018, the
petitioner called upon respondent No.1 to handover the project site within a
period of 07 days along with the project documents and drawings. This caused
respondent No.1 to file another application under Section 20 of the 1940 Act on
18.08.2018 praying for the contractual disputes between the parties to the said
contract to be referred to arbitration. Along with the said application,
respondent No.1 filed an application for interim injunction, praying for a
restraint against the petitioner from dispossessing respondent No.1 from the
project site. Vide ad-interim order dated 18.08.2018, the learned Civil Court
restrained the petitioner from dispossessing respondent No.1 from the project
site. For the purposes of this petition, it is unnecessary to discuss any
further the proceedings pursuant to the second application under Section 20 of
the 1940 Act filed by respondent No.1.
9. Be
that as it may, after an inter parte hearing on respondent No.1's application
for interim injunction filed along with its first application under Section 20
of the 1940 Act, the learned Civil Court vide order dated 17.05.2019 restrained
the petitioner from encashing the performance guarantee, and also directed the
parties to maintain status quo at the project site till the conclusion of the
arbitration proceedings. It may also be mentioned that vide the said order
dated 17.05.2019, the learned Civil Court had also allowed respondent No.1's
application under Section 20 of the 1940 Act and referred the matters in
dispute between the parties to the said contract to arbitration. Presently, the
arbitration proceedings between the said parties are pending.
10. Through
the instant civil revision petition, the petitioner has assailed the order
dated 17.05.2019 passed by the learned Civil Court to the extent of allowing
respondent No.1's application for interim injunction.
11. Learned
counsel for the petitioner, after narrating the facts leading to the filing of
the instant civil revision petition, submitted that the performance guarantee
dated 10.01.2012 furnished by respondent No.2 at the instance of respondent
No.1 for 5% of the contract price; that the said guarantee was irrevocable and
independent in nature; that it is well settled that a contract of guarantee has
to be treated independently from the underlying contract; that such a guarantee
has to be encashed in accordance with its own terms and conditions without
reference to the terms of the underlying contract; that in the performance
guarantee dated 10.01.2012, the guarantor/respondent No.2 waived all objections
and defences under the underlying contract, and agreed to irrevocably and
independently pay to the petitioner without any delay upon the petitioner's
first written demand without any cavil or arguments against the petitioner's
written declaration that respondent No.1 has refused or failed to perform its
obligations under the contract; that the said guarantee also provided that the
petitioner shall be the sole and final judge for deciding whether respondent
No.1 has duly performed its obligations under the contract or has defaulted in
fulfilling its obligations; and that the order passed by the learned Civil
Court to restrain the encashment of the performance guarantee is contrary to
the law laid down by the superior Courts.
12. Learned
counsel for the petitioner further submitted that the contract dated 24.01.2012
is essentially a contract for the provision of services; that such a contract was
not specifically enforceable in terms of Section 21 of the Specific Relief Act,
1877; that Section 56(f) of the said Act provides that an injunction could not
be granted to prevent the breach of a contract which was not specifically
enforceable; that the learned Civil Court erred by directing the parties to
maintain status quo at the project site till the conclusion of the arbitration
proceedings; and that such an injunction also runs contrary to the law laid
down by the superior Courts. Learned counsel for the petitioner prayed for the
revision petition to be allowed in terms of the relief sought therein.
13. On
the other hand, learned counsel for respondent No.1 submitted that respondent
No.1 had already carried out the excavation works when the allotment of Plot
No.63A was cancelled by the L.D.A.; that after alternative Plot No.66 was
allotted, the project site was changed; that payment against the Interim
Payments Certificates ("IPCs") submitted by respondent No.1 were
substantially delayed; that this delay necessitated respondent No.1 to apply
for an extension of time; that payment against IPC No.9 had been unlawfully
adjusted whereas payment against IPC No.10 was partially released and that too
with a delay of 432 days; that malicious criminal complaints have been lodged
by the petitioner against respondent No.1; that IPC No.15 submitted by
respondent No.1 has not been cleared as yet; that the learned Civil Court erred
by not appreciating that respondent No.1 had a right to remain in possession of
the project site due to its easement rights under Section 60 of the Easement
Act, 1882; that under Section 16 of the Specific Relief Act, 1877 the Court can
direct a contract to be partially performed; that even though an amount of
Rs.34,998,889/- against IPC No.15 has been certified, the petitioner has, till
date, not made the payment against the same; that the advance paid by the
petitioner had been fully utilized by respondent No.1 in furtherance of its
obligations under the contract; and that since the equities weigh heavily in
favour of respondent No.1, the learned Civil Court did not commit any
jurisdictional error by allowing respondent No.1's application for interim
injunction. Learned counsel for respondent No.1 prayed for the revision
petition to be dismissed.
14. I
have heard the contentions of the learned counsel for the contesting parties
and have perused the record with their able assistance. The facts leading to
the filing of the instant civil revision petition have been set out in
sufficient detail in paragraphs 2 to 10 above and need not be recapitulated.
15. I
first propose to deal with the question whether it was lawful for the learned
Civil Court to have granted an injunction to restrain the encashment of the
performance guarantee furnished by respondent No.2 at the instance of
respondent No.1. As mentioned above, the said guarantee was furnished pursuant
to the requirement in clause 32.1 of the Invitation for Bids which forms an
integral part of the contract dated 24.01.2012. The said guarantee is for an
amount of Rs.51,864,749/- and was issued on 10.01.2012. In the said guarantee,
it is provided that it was to remain in full force until respondent No.1
performed its obligations under the contract and the works under the contract
are taken over. It is also provided that the claim for payment under the
guarantee is to be made in writing within the validity period of the guarantee.
The following two clauses of the guarantee are of crucial importance and are
therefore reproduced herein below:-
"We,
Jubilee General Insurance Company Ltd (the Guarantor), waiving all objections
and defences under the Contract, do hereby Irrevocably and Independently
guarantee to pay to the Employer without delay upon the Employer's first
written demand without cavil or arguments any sum or sums up to the amount
stated above, against the Employer's written declaration that the Principal has
refused, or failed to perform the obligations under the Contract, for which
payment will be effected by the Guarantor to Employer's designated Bank and
Account Number.
PROVIDED
ALSO THAT the Employer shall be the sole and final judge for deciding whether
the Principal has duly performed his obligations under the Contract or has
defaulted in fulfilling said obligations and the Guarantor shall pay without
objection any sum or sums up to the amount stated above upon first written
demand from the Employer forthwith and without any reference to the Principal
or any other person."
(Emphasis
added)
16. Generally
performance guarantees are required to be furnished so as to ensure that the
contractor fulfills his obligations under the underlying contract. Calls for
the encashment of such guarantees are made by employers when the contractor
commits a default in the fulfillment of his obligations under such a contract.
Performance guarantees fall under the rubric of documentary credits, and
interference with obligations of the guarantors under such guarantees is on
limited grounds. These grounds include egregious fraud of which the guarantor
has prior notice or irretrievable injustice that would be caused to the
contractor/principal debtor in case of encashment. Such guarantees are
considered to be independent of the underlying contract, and interference by
Courts with obligations of the guarantors primarily depend on the words
employed in such guarantees. In the case of Shipyard K. Damen International v.
Karachi Shipyard and Engineering Works Ltd. (PLD 2003 SC 191), it was held
inter alia that the rights and liabilities of the parties are to be determined
with reference to the terms and conditions of the guarantees.
17. The
contractual disputes between the petitioner and respondent No.1 are presently
the subject matter of arbitration proceedings, and it will be in such
proceedings that the arbitral Tribunal would give a finding as to whether
respondent No.1 had committed a default in the fulfillment of its obligations
under the contract. However, the terms of the performance guarantee dated
10.01.2012 do not make its encashment contingent on the finding of the arbitral
tribunal that respondent No.1 had committed a default. The contention of the
learned counsel for respondent No.1, that since the question as to whether
respondent No.1 had committed a default in the fulfillment of its obligations
under the contract is yet to be determined by the arbitral tribunal, the
petitioner's demand for the encashment of the guarantee is premature and
irreconcilable with the terms of the performance guarantee dated 10.01.2012.
The said performance guarantee requires the petitioner to make a declaration
that respondent No.1 had refused or failed to perform its obligations under the
contract. For the purposes of making a demand for the encashment of the said
guarantee, it is explicitly provided that the petitioner shall be "the
sole and final judge" for deciding whether respondent No.1 has duly
performed his obligations under the contract or has defaulted in fulfilling the
said obligations. If this Court were to ignore the said provision in the performance
guarantee and make the encashment of the guarantee contingent on the finding by
the arbitral Tribunal that respondent No.1 had committed a default in the
fulfillment of its contractual obligations, it would amount to this Court
re-writing the terms of the guarantee. This a Court cannot do. None of the
terms of the said guarantee are such as to be termed as uncontainable, absurd,
inconsistent, or vague. In the cases of Braganza v. BP Shipping Limited (2015
SCMR 742), System Company v. MTU Middle East FZE (PLD 2019 Sindh 382), Green
Group of Hotels v. Municipal Corporation, Peshawar (2017 MLD 257) and Pakistan
Industrial Credit and Investment Corporation Ltd. v. Khairpur Sugar Mills Ltd.
(2012 CLD 1192), it was held inter alia that Courts cannot rewrite contracts executed
by parties with their own free consent. In the case of Montage Design Build v.
The Republic of Tajikistan (PLD 2015 Islamabad 13), this Court held as
follows:-
"31.
Before parting with this judgment, it is pertinent to observe that an
irrevocable and unconditional guarantee is like any other contract, standing on
the foundation of entering into binding contractual obligations voluntarily and
the principle of freedom to contract. Once the parties have executed binding
commitments, they are expected to observe certain standards of behavior. It has
been observed that the Insurance companies promptly issue unconditional
Guarantees and when the demand is made, many avoid fulfilling their absolute
commitments and undertakings. They delay payment of the guaranteed amount and
allow the parties an opportunity to seek the intervention of the Courts in the
hope that they might obtain an injunction. Similarly, contractors in their
exuberance for the release of advance payments under a contract, cause unconditional
guarantees to be furnished as security, but when a demand is raised, expect
that the Courts would come to their rescue, despite the unambiguous language of
the guarantee. It may be understood that Courts have no power to interfere
with, alter, vary or in any other manner change the intention of the parties
who voluntarily enter into binding contractual commitments. Nor can the Courts
rewrite or defeat the terms agreed and explicitly stipulated in a contract.
Granting an injunction and restraining the encashment of an irrevocable and
unconditional guarantee, except in the exceptional circumstances as discussed
above, would amount to changing the nature of the agreed terms and conditions
of the guarantee, and frustrating the intention of the parties. It is for this
reason that the Courts are slow and exercise restraint in granting injunctions.
It is for the parties, particularly the Banks and Insurance companies, to
exercise care and caution when issuing unconditional and irrevocable
guarantees. It is expected that they take sufficient care in securing their
interests at the time of issuing irrevocable and unconditional guarantees,
instead of avoiding their absolute obligations by delaying payments."
18. Clause
32.1 of the Invitation for Bids, which forms part and parcel of the contract
documents, provides inter alia that the performance security was to be
furnished in the form set out in the conditions of the contract. The
performance guarantee dated 10.01.2012 furnished by respondent No.2 at the
instance of respondent No.1 in fulfillment of its obligations under clause 32.1
ibid conforms to the form of the guarantee in the conditions of the contract.
Therefore, right from the stage of the execution of the contract, respondent
No.1 was or ought to have been aware of the terms on which the performance
guarantee could be encashed.
19. True,
it is within the realm of possibilities that after the performance guarantee is
encashed by the petitioner, the arbitral tribunal may hold that respondent No.1
had not committed any default of its obligations under the Contract or that
default committed by respondent No.1 did not result in any monetary loss to the
petitioner. In such a scenario, respondent No.1 would be entitled to be repaid
the amount encashed by the petitioner. The petitioner's declaration that
respondent No.1 has committed a default of its obligations under the Contract
has been made conclusive only for the purpose of making a demand for the
encashment of the performance guarantee. Such a declaration is not binding on
the arbitral tribunal which may, on the basis of the evidence on the record,
come to a different conclusion.
20. Letter
dated 29.12.2017 from respondent No.2 to respondent No.1 informing the latter
as to the demand made by the petitioner for the encashment of the guarantee
mentions that the petitioner had declared that respondent No.1 had failed to
fulfill its contractual obligations. Since respondent No.1, as the principal
debtor, was well aware that the performance guarantee dated 10.01.2012 could be
encashed on the basis of a declaration made by the petitioner to the effect
that respondent No.1 had defaulted in fulfilling its obligations under the
contract, and that the petitioner had been made the sole and final judge for
deciding whether respondent No.1 had committed such default, I am of the view
that the learned Civil Court erred by issuing an injunction to restrain the
encashment of the said performance guarantee. In holding so, I derive guidance
from the following case law:-
(i) In the
case of Standard Construction Company (Pvt.) Limited v. Pakistan through
Secretary Ministry of Communications (2010 SCMR 524), it was held as follows:-
"5.
The bank guarantees, generally, contain in their contents whereby the
guarantor undertakes to agree irrevocably and unconditionally to the payment to
the beneficiary/employer the amount mentioned therein and the demand of the
beneficiary is deemed to be a conclusive evidence and who is considered as the
sole judge to do so regarding the failure of the principle to have not complied
with or fulfilled the requirements of the brief/agreement. However, there are
certain guarantees, which in their contents without mentioning the demand as
the conclusive evidence or the beneficiary to be the sole judge, prescribe
certain eventualities on the happening whereof the beneficiary is entitled to
the demand of the encashment of the guarantee. While going through the
aforesaid three bank guarantees we find that the first bank guarantee amounting
to Rs.18 million regarding the pre-bid in addition to the terms "it is
hereby guaranteed irrevocably and unconditionally to pay to you forthwith,
without prior course to the Bidder" it further prescribes "It is
agreed that any such demand made hereunder by you shall be conclusive evidence
of the Bidder's failure to comply with or fulfil the requirements of the Brief
as set out above." Such averments, as contained in the above guarantee,
made the beneficiary as the sole judge and its mere demand would be sufficient
to entitle it to the encashment of the bank guarantee without any reservation
on the part of the guarantor."
(ii) Recently
in the case of Husein Industries Ltd. v. Sui Southern Gas Company Ltd. (PLD
2020 Sindh 551), the Hon'ble High Court of Sindh held as follows:-
"7.
The Courts in Pakistan have generally construed Mobilization Guarantees as not
being subject to a restraining order even if there is a dispute between the
parties to the underlying contract. However, in cases of guarantees other than
Mobilization Guarantees, the Courts have granted or refused injunction to
restrain encashment depending upon the literal words used in the guarantee. If
the bank guarantee contains a stipulation to the effect that the surety shall
pay "if default is committed by the principal debtor", an injunction
may follow on the theory that until 'default' is proved by evidence, there is
no default. On the other hand, where the language used in the bank guarantee is
to the effect that the guaranteed sum is payable unconditionally; or
irrespective of any dispute between the creditor and principal debtor; or that
the creditor shall be the sole judge of the alleged default; the Courts have
refused to grant injunction to restrain encashment unless the plaintiff
demonstrates fraud by the creditor which is in the knowledge of the bank, or
unless it is a case giving rise to a special equity in favour of the
plaintiff."
(iii) In the
case of Atlas Cable (Pvt.) Limited v. Islamabad Electric Supply Company Limited
(2016 CLC 1677), I had the occasion to hold as follows:-
"48.
Irrevocable and unconditional bank guarantees are normally couched in a
language whereby the bank undertakes to give money to the beneficiary on
demand, without demur or protest. If a bank guarantee is unconditional
stipulating that the bank should pay, on demand, without demur and that the
beneficiary shall be the sole judge not only on the question of breach of
contract but with respect to the amount of loss or damage, the obligation of
the bank has to be discharged in the manner provided in the bank guarantee.
When such a demand is made, the bank is not permitted to probe into the
disputes between the parties. The courts will not interfere directly or
indirectly to withhold payment, otherwise trust in commerce, internal and
international, would be irreparably damaged."
(iv) In the
case of Global Energy and Commodity Exchange Group Italy SPA (GECX GROUP) v.
Trading Corporation of Pakistan (2013 CLD 681), the Hon'ble High Court of Sindh
held as follows:-
"19.
In the case in hand I have carefully examined the terms and conditions of bank
guarantee and also reproduced the relevant clauses in which it was clearly
agreed that the guarantee was unconditional and buyer was the sole judge to
decide whether the seller has performed the contract and fulfilled the terms
and conditions of the contract. The guarantor also agreed to honour the
guarantee as, directed by the buyer on the date of receipt of demand in writing
without any question whatsoever and without oral or written reference to the
seller. Keeping in view the dictum laid down by the Hon'ble Supreme Court, it
is clear beyond any shadow of doubt that unqualified terms of guarantee cannot
be interfered with irrespective of existence of dispute nor interim of
injunction restraining payment thereunder can be granted. The commitment of
banks must be honoured free from interference of the court. As a result
thereof, I have no hesitation in my mind to hold that no case is made out for
passing or confirming the restraining order against the encashment of
performance guarantee."
(v) In the
case of Mahatma Gandhi Sahakara Sakkare Karkhane v. National Heavy Engg. Coop.
Ltd. (AIR 2007 SC 2176), the Supreme Court of India, after referring to the
provisions of a bank guarantee which provided that the purchasers shall be the
sole judge of and as to whether the amount of the bank guarantee had become
recoverable from the sellers or whether the sellers had committed any default
in the terms and conditions of the agreement, held as follows:-
"18.
The sole discretion is conferred on the purchasers as to whether the amount
of bank guarantee has become recoverable from the sellers or whether the
sellers have committed any breach of the terms and conditions of the said
agreement. The right of the purchaser to recover from the guarantor the
guaranteed amount shall not be affected or suspended by the reasons of the fact
that any dispute or disputes have been raised by the sellers with regard to their
liability or that the proceedings are pending before any tribunal or court with
regard thereto or in connection therewith.
19.
The respondent cannot be allowed to contend that there is a dispute as to
whether it had failed to conduct the trial test of the sugar plant by 24th
July, 2003 and therefore bank guarantee cannot be invoked. The acceptance of
the argument would make Clause 2 of the bank guarantee totally meaningless and
inoperative. The guarantor essentially agreed that the purchasers alone shall
be the sole judge in the matter as to whether the amount of bank guarantee has
become recoverable from the sellers or whether the seller had committed any
breach of the terms and conditions of the agreement. The dispute, if any,
between the parties with regard to the liability in any proceedings either
before the arbitral tribunal or court in no manner affects the right of the
purchaser to invoke the bank guarantee and realize the guaranteed sum from the
guarantor."
(vi) In the
case of Hindustan Steelworks Construction Ltd. v. Tarapore & Co. (AIR 1996
SC 2268), it was held as follows:-
"Whether
the bank guarantee is towards security deposit or mobilization advance or
working funds or for due performance of the contract if the same is
unconditional and if there is a stipulation in the bank guarantee that the bank
should pay on demand without a demur and that the beneficiary shall be the sole
judge not only on the question of breach of contract but also with respect to
the amount of loss or damages, the obligation of the bank would remain the same
and that obligation has to be discharged in the manner provided in the bank
guarantee."
(vii) In the
case of Hindustan Steel Workers Construction Ltd. v. G.S. Atwal & Co.
(Engineers) (Pvt.) Ltd. (AIR 1996 SC 131), it was held as follows:-
"6.
On a perusal of the relevant clauses of the Guarantees, it is evident that the
Bank has unconditionally and irrevocably agreed and undertaken to pay to the
appellant on demand the sums specified therein. It is further seen that the
amount should be paid without demur and without requiring the creditor (the
appellant) to invoke any legal remedy and it is further specifically provided
that the appellant shall be the sole judge of and as to whether the respondent,
a party to the contract, has committed any breach and the extent of the loss
and damages etc. caused to the appellant. It is stated that the decision of the
appellant as to the outstanding amount due will be final and binding. We are
of the view that the Guarantees furnished by the Bank to the appellant are
unconditional and the appellant is the sole judge regarding the question as to
whether any breach of contract has occurred and, if so, the amount of loss to
be recovered by the appellant from the respondent. The entire dispute is
pending before the Arbitrator. Whether and if so, what is the amount due to the
appellant is to be adjudicated in the arbitration proceeding."
21. Vide
order dated 17.05.2019, the learned Civil Court had also directed the
contesting parties to maintain status quo at the project site till the
conclusion of the arbitration proceedings. The contract executed between the
petitioner and respondent No.1 was for the "Engineering, Procurement and
Construction of Mix Used Development." Essentially the said contract was
for the provision of services. Respondent No.1's entry onto the project site
was only on the basis of the said contract. Section 21(a) of the Specific
Relief Act, 1877 provides that a contract for non-performance of which
compensation is an adequate relief cannot be specifically enforced.
Furthermore, Section 56(f) of the said Act provides that an injunction cannot
be granted to prevent the breach of a contract the performance of which would
not be specifically enforced. Before a construction contract can be ordered to
be enforced, it has to be held that compensation in money is not the adequate
relief. It cannot be disputed that a contract, which cannot be enforced by a
decree for specific performance, cannot be negatively enforced by issuance of
an injunction. In the face of the petitioner's demand for respondent No.1 to
vacate the project site, the latter could not seek an injunction which would
have the effect to remain on the project site and proceed with the balance
works as this would amount to specifically enforcing a contract of construction
which is impermissible in law. Therefore, the learned Civil Court erred by
directing the maintenance of status quo at the project site till the conclusion
of the arbitration proceedings. In holding so, I derive guidance from the
following case law:-
(i) In the
case of Lahore Stock Exchange Ltd. v. Hassan Associates (2010 MLD 800), the
Hon'ble Lahore High Court held that a contract for the designing and
supervision of construction of a building proposed to be raised and constructed
was not a contract which could be specifically enforced since the entitlement
of the plaintiffs/respondents could be measured in pecuniary terms.
Furthermore, it was held that in view of Section 56(f) of the Specific Relief
Act, 1877, no injunction could be granted to restrain the breach of such a
contract. For the purposes of clarity, paragraph 4 of the said report is
reproduced herein below:-
"4.
Counsel for the parties have been heard and record appended with these
petitions perused. It is an admitted fact on record that the original agreement
executed inter se the parties pertained to the hiring of the services of the
respondents as Architects for designing and supervision of proposed
constructions. There was a settled consideration payable to the respondents
under the said agreement, dated 3-5-1997 which was modified vide the
supplementary agreement, dated 11-10-2001 on the face of it such an agreement
was not specifically enforceable as the only entitlement of the respondents qua
consideration was mentioned, thus, stood measured in pecuniary terms. The
agreement pertained to and was dependent upon the personal professional qualification
of the respondents and ran into minute and numerous details qua designing and
planning, which could never be over seen by any Court of law. Such elemental
principle in this behalf is enunciated in section 21 of the Specific Relief
Act, 1877 and, therefore, in view of section 56(f) of the Specific Relief Act
no injunction could be granted to restrain the breach thereof. It has been
noticed with great dismay that the impugned judgment has been passed in
violation of the clear unequivocal, ancient and settled elemental principle of
law. In this view of the matter the impugned judgment for grant of injunction
is not sustainable in law."
(ii) In the
case of District Council, Gujrat v. Iftikhar Ahmad (1998 MLD 1461), a contract
for the collection of cattle fee was held to be a contract the specific
performance whereof could be refused under Section 21 of the Specific Relief
Act, 1877. Furthermore, it was held that the relief of injunction could also
not be granted in the event of a breach of such a contract. A suit for damages
was held to be the appropriate remedy in case of where such a contract is
terminated.
(iii) In the
case of Qasimabad Enterprises v. Province of Sindh (1998 CLC 441), a contract
for a joint venture scheme for the construction of shops, flats and bungalows
in the Qasimabad Housing Scheme was held by the Hon'ble High Court of Sindh to
be a contract which could not be specifically enforced. In the said judgment,
it was also held that an injunction cannot be granted to prevent the breach of
a contract, the performance of which would not be specifically enforced.
22. The
aforementioned judgments were authored by Hon'ble Judges who rose to grace the
Hon'ble Supreme Court, therefore the ratio in the said cases deserve reverence
and respect. Law to the said effect was also laid down in the cases of
Universal Trading Corporation (Pvt.) Ltd. v. Beechem Group PLC (1994 CLC 726),
Hussain Naseer v. Shamim Yaqoob (1989 CLC 2125) and PIA Corporation v. Hazir
(Pvt.) Ltd. (PLD 1993 Karachi 190).
23. Having
gone through the impugned order dated 17.05.2019, I have noticed that before
granting an interim injunction, the learned Civil Court did not determine as to
whether the three essential ingredients for the grant of an interim injunction
had been satisfied in the case at hand. This is another jurisdictional
irregularity which warrants interference with the said order. Had the learned
Civil Court bothered to determine whether the ingredient regarding irreparable
loss had been satisfied in the case at hand, it would have seen that the loss
which respondent No.1 was alleged to have suffered at the hands of the
petitioner was monetary loss, which cannot be termed as an irreparable loss. In
the case of Dewan Petroleum (Pvt.) Ltd. v. Oil and Gas Investment Limited (2019
CLC 1486), the learned Civil Court had granted an interim injunction without
giving any finding regarding the existence of the pre-conditions necessary for
the grant of such an injunction. In the said case, I had the occasion to hold
as follows:-
"27.
It is well settled that temporary injunction cannot be granted in cases where
applicant did not have a good prima-facie case; the balance of convenience was
not in his favour; and that the loss he would suffer if the injunction was not
granted was not irreparable and could be measured in terms of money. It appears
that the learned Civil Court did not apply its judicious mind to the principles
on which an interim injunction can be granted. There is, for instance, no
mention in the said order as to the three ingredients for the grant of an
interim injunction having been satisfied.
28.
Under Section 41(b) read with the Second Schedule to the 1940 Act, the Court
has the power to issue interim injunctions for the purpose and in relation to
arbitration proceedings. The principles for the grant of an interim injunction
under Section 41(b) read with the Second Schedule of the 1940 Act are the same
as the ones applicable to interim injunctions granted under Order XXXIX, Rules
1 and 2, C.P.C. In the case of Pakistan Railways v. Four Brothers International
(Pvt.) Ltd. (PLD 2016 SC 199), it has been held that an injunctive order
against the recovery of amounts passed under Section 41(b) of the 1940 Act
without examining the three ingredients for the grant of injunction i.e.
prima-facie arguable case, balance of convenience and irreparable loss, is not
sustainable in law. In the said case, the matters in dispute between the
parties were referred to arbitration, but the interim injunction passed by the
learned Civil Court as well as the learned Revisional Court were vacated.
29. It
will be for the respondent to prove in the arbitration proceedings that the
appellant had breached the provisions of the JOA by making unjustified cash
calls or that the amounts paid by the respondent in response to such cash calls
had not been used in furtherance of the obligations of the working interest
owners in the Safed Koh project. In the event the respondent is able to prove
this, it would have a case for the recovery for an ascertained amount against
the appellant. In this view of the matter, it cannot be held that if the
interim injunction was not granted to the petitioner, it would suffer
irreparable loss. In the cases of Tauseef Corporation (Pvt.) Ltd. v. Lahore
Development Authority (2002 SCMR 1269), Al-Tamash Medical Society v. Dr. Anwar
Ye Bin Ju (2019 CLC 1), and Maxim Advertising Company (Pvt.) Ltd. v. Province
of Sindh (2007 MLD 2019), the Superior Courts have held that where loss was
ascertainable in terms of money, then it could not be treated as a case of
irreparable loss. In the case of Haji Khan v. Government of Sindh (1990 MLD
155), the Hon'ble Mr. Justice Wajihuddin Ahmad (as he then was) had the
occasion to hold as follows:-
"The
crucial point in the case was the question of irreparable loss. Since money was
involved and loss, if any, to the plaintiffs could have been assessed in terms
of money, question of irreparable loss hardly arose but all that the learned
Judge said on the subject was that "valuable right has been created in
favour of the plaintiffs, by the said contract, therefore, in my humble opinion
breach of the said contract cannot be adequately compensated in terms of
money". Manifestly, contracts involving collection of monetary benefits,
which themselves have been obtained on specific monetary considerations, on
principle, cannot involve irreparable loss because such loss, inherently, means
and implies only such loss as is incapable of being calculated on the yardstick
of money. Unless all the required ingredients of prima facie case, balance of
convenience and irreparable loss to the aggrieved party are found to subsist,
no Injunction under Order XXXIX, Rules, 1 and 2, C.P.C. can issue."
30. It
is well settled that all the three ingredients for the grant of an injunction
must co-exist and if any one of such ingredients is missing in the case, the
litigant would not be entitled to the grant of a temporary injunction.
Reference in this regard may be made to the law laid down in the cases of Puri Terminal
Ltd. v. Government of Pakistan (2004 SCMR 1092), Imtiaz Ahmad v. Muhammad
Shoaib Shah (2015 CLC 1121), Mst. Azra Parvez v. Sheikh Ashfaq Hussain (2015
CLC 1695), M.Y. Corporation (Private) Ltd. v. Erum Developers (PLD 2003 Karachi
222), Managing Committee, Revenue Employees Cooperative Housing Society v.
Secretary, Cooperative Societies, Government of Punjab (2001 CLC 838), Zakaria
Dada v. Maneck Byramji Javat (1992 CLC 345) and Haji Khan v. Government of
Sindh (1990 MLD 155)."
24. In
view of the above, the instant revision petition is allowed. Consequently, the
impugned order 17.05.2019 to the extent of allowing respondent No.1's
application under Order XXXIX, Rules 1 and 2 C.P.C. is set-aside and the said
application is dismissed. There shall be no order as to costs.
KMZ/188/Isl. Order
accordingly.