2021 C L C 515
[Lahore]
Before Muhammad Qasim Khan, CJ
Messra SPARCO CONSTRUCTION COMPANY----Petitioner
Versus
PROVINCE OF PUNJAB and others----Respondents
Writ Petition No.23950 of 2020, decided on 3rd December, 2020.
(a) Punjab Procurement Rules, 2014---
----R.5---Constitution of Pakistan, Art.199---Foreign funded project ---
Technical and financial bids---Technical Evaluation Committee declared the bid
submitted by the petitioner-company and its joint venture company as
non-responsive---Petitioner-company challenged its disqualification from the
bid process by filing a constitutional petition before the High
Court---Maintainability---Project in question was regulated under a loan
agreement entered into between the Government of Pakistan and an international
financial institution--- In the bid process the terms of the loan agreement and
that of the bid documents were also to be applied according to the satisfaction
of the international financial institution itself, therefore, on the face of it
there was no applicability of Punjab Procurement Rules 2014 ('the 2014 Rules')
in the whole project---As the loan agreement had been executed between the
Government of Pakistan and an international financial institution, the present
constitutional petition was not maintainable --- High Court dismissed the
constitutional petition with the directions that the Provincial Government
should form a Committee to minutely probe into the entire process of awarding
of the project and bring it to the notice of the international financial
institution as well; that the said Committee shall see if there was any misuse
of authority in the entire process at any level, whether transparency was
properly taken care of, and that proper process was adopted in the project;
and, that formation of said Committee shall not mean stay of further process on
the project.
Messrs
Power Construction Corporation of China Ltd. through Authorized Representative
v. Pakistan Water and Power Development Authority through Chairman WAPDA and 2
others PLD 2017 SC 83 and Suo Moto Case No.5 of 2010 PLD 2010 SC 731 ref.
(b) Civil Procedure Code (V of 1908)---
----O.I, R.9---Constitution of Pakistan, Art. 199 --- Misjoinder or
non-joinder of necessary parties --- Foreign funded project --- Technical and
financial bids---Technical Evaluation Committee declared the bid submitted by
the petitioner-company and its joint venture company as
non-responsive---Petitioner-company challenged its disqualification from the
bid process by filing a constitutional petition before the High
Court---Maintainability---Like the petitioner-company the other company with
which the petitioner had a joint venture, was also part of the bid, thus, it
must also be adversely affected by the impugned action of procuring authority,
as such, instead of citing the joint venture company as a respondent, it must
have been arrayed as one of the petitioners in the present constitutional
petition, which has not been done, thus the consequential inference would go
against the petitioner---Furthermore, the claim of the petitioner had been that
it fulfilled the requisite evaluation and qualification criteria set down in
the Biding Document, as some projects identical to the present one were
completed by certain groups and companies working under it---If that was so,
then such groups and companies were necessary and proper party to present
proceedings, but none of the said groups or companies was arrayed as a party in
the constitutional petition---Inference which could be drawn in such
circumstances was that those groups or companies, which the petitioner claimed
worked under it, were either not interested/involved in the bid process, or
were not supporting the stance of the petitioner in any manner --- Procuring
authority appeared to be well within its right to urge that in fact those
groups or companies had no liaison with the petitioner's joint venture ---
Present constitutional petition was not maintainable due to misjoinder and
non-joinder of necessary parties and was consequently dismissed.
Qazi
Misbah ul Hassan and Muhammad Zain Qazi for Petitioner.
Malik
Abdul Aziz Awan, Additional Advocate-General.
Asad
Ali Bajwa, Deputy Attorney General-I.
Mustafa
Ramday, Nadia Hafeez and Zoe K. Khan for Respondent No.3.
Barrister
Ahmad Pansota and Shah Jehan Khan for Respondent No.4.
ORDER
MUHAMMAD
QASIM KHAN, C.J.----Precisely the
facts of the case are that a project with the name "Jalalpur Irrigation
Project No.2 (JIP2)" for construction of main Canal (RD 52+0(l0 to RD
225+500), including distribution system and Flood Carrier Channels, Cross
Drainage Structures, Road Bridges, etc. (Contract No.JIP/WKS/ICS-P2), was
launched, where-for, bids were invited for award of contract and a Loan
Agreement was entered into between the Government of Pakistan and the Mian Development
Bank (ADB) to carry out the mid project. The petitioner after forming a joint
venture with respondent No.5 (Top International Engineering Corporation (TIEC)
of Peoples Republic of China), jointly participated in the tender by submitting
their technical and financial bids. After opening technical bids, the Technical
Bid Evaluation Committee formed by respondents Nos.2 and 3 declared the
petitioner and its Joint Venture Company as non-responsive on multiple grounds,
whereas, respondent No.4 was declared as successful bidder. Disqualification of
petitioner's joint venture in the Technical Bid and the process of finalizing
the contract in favour of respondent No.4, is in fact the grievance being
voiced through the instant writ petition.
2. The
contention of learned counsel for the petitioner is that qualification criteria
set down in section 2.4.1 of the Bidding document required sufficient
experience and minimum two successful/completed contracts identical to the one
in hand, within last ten years, was fully met with by the petitioner. The
petitioner also fulfilled the requirement as set in section 2.4.2 of the said
document, but in violation of PPRA Rules, on both these aspects, the petitioner
was disqualified and was not even provided the detailed reasons for
non-considering of petitioner's documents and that the financial bid of
respondent No.4 which is rupees one billion higher than the bid submitted by
the petitioner, is being accepted. Lastly, it was argued that since no
Grievance Redressal Committee had been constituted under Rule 67 of the PPRA
Rules, therefore, the petitioner having been left with no remedy, hence the
writ petition is maintainable.
3. On
the other hand, during arguments the learned counsel for the respective
respondents raised preliminary objections i.e. terms and conditions of
financial arrangement between the Government of Pakistan and the Asian
Development Bank (ADB) whereby the loan for JIP has been granted by ADB, have
overriding effect and prevail over Punjab Procurement Rules, 2014 (PPRA), which
exception is envisaged by Rule 5 of PPRA Rules, 2014. Secondly, the ADB is not
an institution operating or carrying on its functions relating the affairs of
Federal or Provincial governments in Pakistan, as such, on both above grounds
the writ petition is not maintainable. On factual aspects, the stance of the
respondents is that requirements as envisaged in Clauses 2.4.1 and 2.4.2 were
not complied with by the petitioner, as the joint venture of the petitioner at
the relevant time had submitted experience of other companies by alleging that
those were part of the petitioner's joint venture group, thus, they could not
claim to have fulfilled the pre-requisites of a valid bid. Lastly, that the
result of technical bid evaluation was duly comminuted to all concerned through
its publication in the newspaper as well as its display on websites of
Irrigation Department, PPRA and the ADB, therefore, the petitioner being
disqualified from the very beginning, could not claim that his bid was of lesser
amount than the one submitted by other contestants
4 Heard.
Record perused.
5. This
court while entertaining this writ petition and issuing notices to the respondents
was mainly influenced by the argument that procedural as also technical aspects
of the bid process were manoeuvred in favour of other parties contesting the
bid and that entire process was being carried out under PPRA. Further that as
the bid offered by the petitioner was rupees One billion (approximately) less
than the bid offered by respondent No.4, therefore, apparently, there appeared
to be some foul play, which could have resulted in colossal loss to the
national exchequer. But, having heard the learned counsel for the respective
parties, scanning the relevant record and analyzing the last on the subject,
the admitted facts remain:-
(a) The
project "Jalalpur Irrigation Project No.2 (JIP2)" for construction of
main canal RD 52+000 to RD 225+500, Contract No. JIP/WKS/ICS-P2), was to be
carried out by the Province of the Punjab through its Irrigation Department;
b) For
the said project, a Loan agreement was entered into between Government of
Pakistan and the Asian Development Bank (ADB);
c) Bids
were invited by adopting the mode of "Single Stage Envelope Bidding
Procedure";
d) The
petitioner formed a joint-venture with respondent No.5 with name as
"TIEC-SPARCO JV" and participated in the tender process;
e) The
Technical Bid Evaluation Committee through its report dated 08.11.2019 declared
TlEC-SPARCO JV as non-responsive, whereas, respondent No.4 and M/s. Descon
Engineering Limited, were declared successful bidders in the technical bids,
out of eight participants.
As shall be seen from the above, on the face of it, the mode, mechanism
or the procedure adopted in the process right from initiation till conclusion
or finalization of the bid has not been questioned by any of the party.
Although, the petitioner has pleaded violation of PPRA Rules, but has not
questioned that the loan agreement was entered into between the Government of
Pakistan and the Asian Development Bank, which undisputedly is an international
financial institution. It has not been disputed that the entire process was
initiated within the bounds of the loan agreement, as also according to the
terms and conditions satisfactory to the Asian Development Bank. This fact is
mentioned in the BIDDING DOCUMENT itself, calling bids for the project.
Therefore, the argument of learned counsel for the petitioner about purported
violation or infringement of PPRA Rules, 2004 in the process, subject matter of
the instant writ petition, has no legs to stand on for the simple reason that
as the entire matter was being regulated under a loan agreement entered into
between the Government of Pakistan and the Asian Development Bank and further
in the bid process the terms of the said loan agreement and that of the bid
documents were also to be applied according to the satisfaction of Asian
Development Bench itself, therefore, on the face of it there was no
applicability of PPRA Rules in the whole project. In this respect specific
reference may also be made to Rule 5 of the Punjab Procurement Rules, 2009,
which precisely reads as under: -
"5.
International and inter-governmental commitments of the Federal Government. -
Whenever
these rules are in conflict with an obligation or commitment of the Federal
Government arising out of an international treaty or an agreement with a State
or States, or any international financial institution the provisions of such
international treaty or agreement shall prevail to the extent of such
conflict."
In view of the above factual and legal aspects, there remains no
ambiguity to observe that as a matter of fact in the circumstances where the
loan agreement has been executed between the Government of Pakistan and an
international financial institution, the writ petition is not maintainable.
Guidance is sought from the judgment of the Hon'ble Supreme Court of Pakistan
in the case "Messrs Power Construction Corporation of China Ltd. through
Authorized Representative v. Pakistan Water and Power Development Authority
through Chairman WAPDA and 2 others" (PLD 2017 Supreme Court 83), wherein
the apex Court with specific reference to Rule 5 of the PARA Rules, 2014,
observed that the provisions of international treaties or agreements shall
prevail, where any provision the PPRA Rules conflicts with an obligation or
commitment of the Federal Government arising out of an international treaty or
agreement. In this view of the matter the remaining arguments of learned
counsel with reference to PPRA Rules, cannot be entertained in these
proceedings under Article 199 of the Constitution of Islamic Republic of
Pakistan, 1973, before this Court.
6 Another
aspect of the matter is that admittedly the petitioner had formed a joint
venture with Top International Engineering Corporation (TIEC) of Peoples
Republic of China, with its branch office House No.17, Street 61, F-8/4,
Islamabad. Therefore, like the present petitioner the said Company being part
of the bid, must also be adversely affected by the impugned action of
respondents, whereby, their joint venture has been disqualified from the bid
process, as such, instead of citing Top International Engineering Corporation
(TIEC) as respondent No.5, it must have been arrayed as one of the petitioners
in the writ petition, which has not been done thus the consequential inference
would go against the petitioner. Furthermore, the claim of the petitioner has
been that it fulfilled the requisite evaluation and qualification criteria set
down in Section 3, Item 2.4.2 of the Biding Document, as some projects were
completed by certain groups and companies working under it. If that is so, then
they were necessary and proper party to these proceedings, but none of such
groups or companies was arrayed as party in this writ petition. The ultimate
inference which can be drawn is that those groups or companies, which the
petitioner claimed to have worked under it, were either not interested/involved
in the said bid process, or were not supporting the stance of the petitioner in
any manner. As such, the respondents appear to be well within their right to
urge that in fact those groups or companies had no liaison with the
petitioner's Joint Venture. In any way, the instant writ petition is also not
maintainable due to misjoinder and non-joinder of necessary parties.
7. As
regards the argument that petitioner had offered a bid of rupees One billion
less than the bid submitted by respondent No.4, this argument on the face of it
looks convincing and attractive, but I am afraid any step of the process of
such a big project cannot be considered in segregation with the rest. Every
stage of the project right from its initiation till calling and submission of
tenders, opening and then finalization of bids is a properly regulated
mechanism and its every next step is netted with the previous one. Keeping this
aspect in mind, unless the petitioner fulfilled its eligibility to submit the
bid, he cannot be allowed to jump over to next stage and plead that as his bid
was of the lesser amount, therefore, he may be considered. Before asking for
it, the petitioner or anyone else, had to establish its very eligibility to
enter in the process. As discussed above, as the petitioner failed to establish
its construction experience etc., required by Clauses 2.4.1 and 2,4.2 of the
bidding document, how so low his bid may be, he could not claim any benefit on
this aspect.
8. For
what has been discussed above, the instant writ petition is dismissed. However,
this court while dismissing the writ petition has mainly confined itself to
legal premises and deliberately has not touched the other allied factual
aspects for some obvious reasons, because definitely it is a big project
involving great financial implications and it was executed by the government
functionaries. The transparency and fairness behind every such project is and
shall be the hallmark of every civilized nation and further the public being
the virtual owners of national exchequer must be kept satisfied that all such
transactions and works are being carried out in a transparent manner,
therefore, by seeking guidance from the judgment in "Suo Motu Case No.5 of
2010" (PLD 2010 Supreme Court 731), considering that as the instant matter
is provincial subject, the Chief Minister, Government of the Punjab, is
directed to immediately form a committee, consisting of men of sound caliber
and integrity from all the concerned agencies, to minutely probe into the
entire process and bring it to the notice of the Asian Development Bank as
well. The Committee, so constituted, shall see whether there was any misuse of
authority in the entire process at any level, whether the transparency and fair
play was properly taken care of and that the proper process was adopted in the
project. It is made clear that simple formation of such committee, shall not
mean stay of further process on the project.
MWA/S-4/L Petition
dismissed.